Usson Energies
Usson-du-Poitou et Bouresse (86)
  PROJECT TIMELINE
 
<< Return
     
  June 2006 : Initial meetings with Usson-du-Poitou municipal authorities
  2006 : Preliminary administrative instruction, local consultations
  February 2007 : Initial meetings with Bouresse municipal authorities
  March 2007 – June 2008 : Impact studies, further consultations
  June 2007 – August 2010 : Assessment of wind potential with the installation of a mast on site
  December 2008 : Requests for building permits submitted
  April – Mai 2010 : 1er Public inquiry
  November – December 2010 : 2nd Public inquiry
  March 2011 : Building permits issued by the prefect
  June 2011 – May 2014 : third party remedies
  End 2014 – Summer 2016 : Preparation of construction works
  September 2016 : Work starts on the construction site
  August 2017 : Wind farm commissioned

 

Type of machines: VESTAS 100
Number of machines: 5
Unit power: 2 MW
Total installed power: 10 MW
Rotor diameter: 100 m
Total height at tip of blade: 150 m
Height of hub: 100 m
Wind speed → start: 10.8 km/h
Wind speed → optimum power: 43,2 km/h
Wind speed → stop: 79,2 km/h

Maintenance: Vestas
Operations monitoring: Atalante Services

 
 